BATH – Three bridges are scheduled for closure beginning May 13, according to the Steuben County Public Works Department.
The bridges are:
· -The
Mill Street bridge in the Town of Cohocton will be closed to all through
traffic for approximately four weeks. The bridge is located between Marks Road and
Erie Street and crosses the Cohocton River. The Mill Street bridge will be
getting a new wooden deck.. There will be no on-site detour.
· -The
Bean Station Bridge in the Town of Wheeler will be closed to all through
traffic for approximately 12 weeks. The bridge is located between Muck and
Dineharts Crossing roads and crosses Five Mile Creek. The Bean Station bridge will
be completely rebuilt with concrete abutments and concrete deck beams. The
on-site detour will consist of Bean Station Road, Depew Road, County Road 77
and Muck Road.
· -The
County Road 333 Bridge in the Town of Campbell will be closed to all through
traffic for approximately 15 weeks. The bridge is located between Campbell
Savona and Tannery Creek roads and crosses Michigan Creek.
The CR 333 bridge will be completely rebuilt with concrete abutments and
concrete deck beams. There will be an on-site detour.